Shotcrete placements

Projects › Skagit Bluff › Ground support › Shotcrete
AMBIENT 4 °C — cold-weather provisions apply. In-place shotcrete must be 10–25 °C at placement, must not fall below 5 °C during the initial four-day curing period, and must not be applied to frozen surfaces or surfaces covered with frost, ice or snow.
DateLocationPlacedRebound7-day28-dayPayment
26 Aug12+440–7018 m³2.4 m³◷ 2 Sep◷ 23 Sepawaiting 7-day
↳ wet process · in-place 14 °C ✔ · surface not frozen ✔ · panels SP-08, SP-09 · cure watch day 1 of 4, min 6 °C ✔
21 Aug12+400–4024 m³3.1 m³31.2 MPa◷ 18 Sep75% releasable
14 Aug12+360–40031 m³4.0 m³28.9 MPa38.1 MPafully releasable
31 Jul12+320–6022 m³2.8 m³24.1 MPa21.4 MPa deficientreduced payment may be considered

Rebound is recorded separately from placed volume, because the Ministry will not pay for volume lost to rebound, sloughing, rejected or discarded shotcrete.

Contractor's Consultant

Independent — not an employee. Shotcrete designed for at least three projects over the last five years. On-site representative is an ACI or CCIL certified concrete technician.

signed field report per site visit — ◷ 26 Aug

Testing laboratory

Independent, qualified, CCIL certified to CSA A283, with a proven record of testing shotcrete on at least five previous projects.

Open results
Layout as specified in SCR-031-shotcrete-placements.md
┌──────────┬────────────────────────────────────────────────────┐
│ NAV      │ Skagit Bluff › Shotcrete            [+ placement]  │
│          ├────────────────────────────────────────────────────┤
│          │ ⚠ AMBIENT 4 °C — cold-weather provisions APPLY     │
│          │   in-place 10–25 °C at placement · not below 5 °C  │
│          │   for 4 days · no frozen/frost/ice/snow surfaces   │
│          ├────────────────────────────────────────────────────┤
│          │ Date   Location  Placed  Rebound  7d    28d        │
│          │ ────────────────────────────────────────────────   │
│          │ 26 Aug 12+440–70  18 m³   2.4 m³  ◷2 Sep ◷23 Sep   │
│          │  wet process · mix ____ · in-place 14 °C ✔         │
│          │  panels SP-08, SP-09 · surface: not frozen ✔       │
│          │  4-day cure watch: day 1 of 4 · min 6 °C ✔         │
│          │ 21 Aug 12+400–40  24 m³   3.1 m³  ✔ 31.2  ◷18 Sep  │
│          │                                    MPa             │
│          │  → 75% releasable · 25% held pending 28d + docs    │
│          │ 14 Aug 12+360–400 31 m³   4.0 m³  ✔     ✔ 38.1     │
│          │  → fully releasable                                │
│          ├────────────────────────────────────────────────────┤
│          │ CONSULTANT (independent, ≥3 projects / 5 yrs)      │
│          │  surface prep observed ▨ · application ▨ · curing ▨│
│          │  signed field report per site visit  ◷ 26 Aug      │
│          │ LABORATORY  CCIL-certified to CSA A283, ≥5 projects│
└──────────┴────────────────────────────────────────────────────┘

Implements spec/03-screens/SCR-031-shotcrete-placements.md · SCR-031 · URL /projects/{project}/shotcrete · Personas QC, TECH · Stories US-QC-006, US-TECH-009