Daily bolt record

Projects › Skagit Bluff › Ground support › Daily bolt record · 26 Aug
MoTI SS 206.91. “Payment for rock bolts will be authorized after installation to the contract specifications and after submittal of the completed Contractor's Daily Rock Bolt Testing and Tensioning Record.” Due within one day of each day of rock bolt operations · 18h remaining
ContractorDynamite Construction Ltd
Date of tensioning26 Aug 2026
Weather / temperatureovercast · 11 °C
Test jack / pump identificationJK-2 / PM-2 — calibrated pair, 14 Aug
BoltLocationLengthBondStartEndLock-offResult
RB-11612+4586.0 mresin08:4108:53140 kNpass
↳ creep readings 1–10 recorded · loss 3.1% · head creep 1.1 mm · resin spin 08:38–08:40
RB-11712+4606.0 mresin09:0009:12140 kNpass
↳ creep readings 1–10 recorded · loss 2.2% · head creep 0.6 mm
RB-11812+4626.0 mresin09:2009:32140 kNpass
RB-11912+4646.0 mresin09:4009:52anchorage failure
loss 12.4% > 10% → replacement RB-119A installed at the contractor's expense. Both stay on the record.
RB-119A12+4646.0 mresin10:1510:27140 kNpass
Totals

12 bolts · 66 m installed (length of bar in the rock) · 11 pass · 1 replaced

Payment

The ROCK BOLTS pay item is blocked until this record is submitted.

Open a test in field mode Calibration register
Layout as specified in SCR-030-rock-bolt-record.md
┌──────────┬────────────────────────────────────────────────────┐
│ NAV      │ Skagit Bluff › Bolt record · 26 Aug   ⏱ due in 18h │
│          ├────────────────────────────────────────────────────┤
│          │ Contractor  Dynamite Construction Ltd              │
│          │ Date of tensioning  26 Aug 2026                    │
│          │ Weather  overcast    Temperature  11 °C            │
│          │ Jack JK-2 · Pump PM-2 (calibrated pair, 14 Aug)    │
│          ├────────────────────────────────────────────────────┤
│          │ Bolt   Loc     Len  Bond  Start End  Lock  Result  │
│          │ ─────────────────────────────────────────────────  │
│          │ RB-116 12+458  6.0  resin 08:41 08:53 140 ✔ pass   │
│          │  creep readings 1–10 ▨   loss 3.1% · creep 1.1 mm  │
│          │ RB-117 12+460  6.0  resin 09:00 09:12 140 ✔ pass   │
│          │  creep readings 1–10 ▨   loss 2.2% · creep 0.6 mm  │
│          │ RB-118 12+462  6.0  resin 09:20 09:32 140 ✔ pass   │
│          │ RB-119 12+464  6.0  resin 09:40 09:52  —  ✕ FAIL   │
│          │  loss 12.4% > 10% → anchorage failure ·            │
│          │  replacement RB-119A at contractor's expense       │
│          ├────────────────────────────────────────────────────┤
│          │ 12 bolts · 66 m installed · 11 pass · 1 replaced   │
│          │ Pay item ROCK BOLTS — payment blocked until this   │
│          │ record is submitted                                │
│          │        [ export record ]  [ mark submitted ]       │
└──────────┴────────────────────────────────────────────────────┘